Borewell Construction - Advice Required - Warangal, Andhra Pradesh

We have drilled a borewell in Warangal District, Andhra  Pradesh (November 2nd,2009) and are planning to install a motor. Installation of the motor is planned for after 2 to 3 months.

Details of borewell:

Depth of borewell 185 Feet, with 6 inch dia. Casing done up to 60 feet. Water was struck from 80 feet with approximately 2 inches of water.

I heared that if we are not installing the motor immediately then the borewell will get dry. Is this true ? If so, could you please clarify as to the reasons for the same?

Regards,

Shyam



Tags:

Comments

1. Dear Mr.Shyam,   Your query

Dear Mr.Shyam,


 


Your query is a good one. I hope that the bore well is flushed properly after drilling to activate the fracture zones. Well, if we do not pump out and activate the water yielding fracture, the fracture may get filled by secondary minerals. Also, If the near by members uses a high H.P pump in thier borewells which is being fed by the same aquifer, then there is all chances of your bore well giving less yield or even gets dried up.


 


Thanks


 


Murali Kochukrishnan


Unit Manager/Sr. Hydrogeologist


Action for Food Production (AFPRO) Task Force-Bhubaneswar


Orissa


 

2. Dear Sir, Thank you for the

Dear Sir,

Thank you for the response.  I am sure this will help me.

3. Borewell Construction - Advice Required

Dear Shyam,

Taking in to consideration the detail given by you regarding the bore well 

Depth of borewell 185 Feet, with 6 inch dia.

Casing done up to 60 feet.

Water was struck from 80 feet with approximately 2 inches of water. 

 This  is a clear indication that the water bearing zone ( aquifer) has been encountered in hardrock nearly 6 m below the casing.

Assuming that

 the casing has not damaged while installation

Adequate length of casing has been installed

And  you have not encountered any clayey or sandy layer while drilling the bore well further

And the bore well was thoroughly flushed after the drilling  operation was over

 

If this is true, then it hardly matters when you install the pump,  provided the well is properly capped and nothing falls in the bore well from top. 

It is possible that the yield in summer months of April & May, may not be the same as encountered while drilling.

The only possibility of the well going dry is if some other person drills another bore well much deeper than the present bore well and manages the de-water the aquifer- It is possible but depends of the terrain   and not  commonly observed.

The possibility of the fractures getting blocked by the clays within it- well this could happen even if the pump is installed, but then you could always develop  the bore well by air jetting,  or you could also add a anticoagulant, like sodium hexameta phosphate solution ( industrial detergent) to the bore well a day before you lower the submersible pump.

The most important thing to do is to first measure the clear depth of the bore well before you lower the pump in the well.

With Reards

Dr. Anil Lalwani

www.wellwaterworks.com

contactus@wellwaterworks.com


Post new comment

The content of this field is kept private and will not be shown publicly.
CAPTCHA
This question is for testing whether you are a human visitor and to prevent automated spam submissions.

Arghyam

6.22-2011.07.01-06